IPP · Hybrid

INTU | BESS IPP, Laingsburg

Laingsburg farmBreaking ground: February 2026Completion date: June 2026

Design Concept

This pre-approved project relies on energy arbitrage. An off-taker has already provided us with a termsheet for R1.95 for the evacuation of all the power. Furthermore, Eskom has furnished us with the CEL (Cost Estimate Letter).

Technical Details

Module DC Nameplate
4 MW
BESS (storage)
20 MWh
Annual production / yield
7.8 GWh
Weather Dataset
Swartberg Substation, Laingsburg

Financial Details

PPA PV Term
20 years
IRR (Internal Rate of Return)
15.7%
Capex
R 115 m
PPA Tariff
R 1.95
PPA Escalation
7%
RoI (Return on Investment)
488%

Projects delivered by Imvelo Energy, the group’s Tier-1 EPC division.

Transparency Notice

To protect client privacy and showcase diverse engineering configurations, some imagery features conceptual 3D and AI designs alongside our physical project portfolio. We build to spec, not just to look good. For references or photos of completed local site handovers, please contact our team directly.