-24.2014, 27.9082Breaking ground: April 2025Completion date: June 2025

Design Concept

A ground-mount PV solution with BESS to offer this client a full off-grid solution. A generator is included.

Technical Details

PV Plant size
120 kWp
BESS (storage)
96 kWh
System type
Off-grid
Yield (kWh/kWp)
1 678

Financial Details

LTO Term
20 years
IRR (Internal Rate of Return)
17.1%
Capex phase 1 (single lodge)
R 2.3 m
Capex phase 2 (35× lodges)
R 52 m
LTO charge (fixed monthly)
R 35k – R 45k / month
LTO Escalation
7%
RoI (Return on Investment)
523%
Monthly savings
R4 218

LTO = Lease-to-own. The R 35k–R 45k / month figure is a fixed monthly LTO charge, not an energy tariff.

Projects delivered by Imvelo Energy, the group’s Tier-1 EPC division.

Transparency Notice

To protect client privacy and showcase diverse engineering configurations, some imagery features conceptual 3D and AI designs alongside our physical project portfolio. We build to spec, not just to look good. For references or photos of completed local site handovers, please contact our team directly.