Agricultural | Laboratory
Back to Projects
Agricultural · Hybrid

Agricultural | Laboratory

Wellington Industrial ZoneCompletion date: 2025

Design Concept

A rooftop PV solution with enough battery storage to last the facility 4 hours of load-shedding. The client will be saving not only on the tariff, but by a diesel saving also. Furthermore there is a saving in the mitigation against loss of production in the factory. The primary saving on the tariff comes from peak-shaving on demand charges, as well as self-consumption to utilise 100% of the solar PV.

Technical Details

PV Plant size
130 kWp
BESS (storage)
120 kWh
System type
Hybrid
Yield (kWh/kWp)
1 678

Financial Details

IRR (Internal Rate of Return)
24.0%
Capex
R 3 163 398
Payback period
4 years, 1 month
Estimated Net Savings
R 9 534 811 (to 2036)
RoI (Return on Investment)
229%

Cashflow Projection

Year-by-year utility bills, savings and cumulative impact.

YearElectricity Consumption (kWh)Utility Bill (before solar) (R)Utility Bill (after solar) (R)Annual Savings (from solar) (R)System Costs (R)Net Savings (R)Cumulative Impacts (R)
2025338 841736 68827 116709 5723 163 398(2 453 826)(2 453 826)
2026338 841788 25628 693759 5630759 563(1 694 263)
2027338 841843 43430 702812 7320812 732(881 531)
2028338 841902 47432 851869 6240869 624(11 907)
2029338 841965 64835 150930 4970930 497918 590
2030338 8411 033 24337 611995 6320995 6321 914 222
2031338 8411 105 57040 2441 065 32601 065 3262 979 548
2032338 8411 182 96043 0611 139 89901 139 8994 119 447
2033338 8411 265 76746 0751 219 69201 219 6925 339 139
2034338 8411 354 37149 3001 305 07101 305 0716 644 210
2035338 8411 449 17752 7511 396 42501 396 4258 040 635
2036338 8411 550 61956 4441 494 17501 494 1759 534 811

Projects delivered by Imvelo Energy, the group’s Tier-1 EPC division.

Transparency Notice

To protect client privacy and showcase diverse engineering configurations, some imagery features conceptual 3D and AI designs alongside our physical project portfolio. We build to spec, not just to look good. For references or photos of completed local site handovers, please contact our team directly.